Case studies

Education

November 11, 2024

Project Value

N/A

Project Duration

9 Weeks

Key Elements

1. Lab Refurbishment and Fit-Out

2. Complete Overhaul of Laboratory Spaces
We removed old furniture and carpets to open up the space, prepped floors for the new installations, added stud walls in targeted areas, and gave all walls and ceilings a full refresh – decorating around 1,485 m² in total.

Plumbing and Fixtures
We installed a new Belfast sink, handling all plumbing to ensure lab readiness.

Specialised Flooring
Installed conductive, slip-resistant flooring incorporating a copper grid system to ensure safety and durability within the lab environment.

3. Deep Cleaning
After the fit-out, a comprehensive deep clean ensured the labs were spotless and ready for immediate use. This included cleaning worktops, cupboards, and hard surfaces in the labs, as well as the walkways (floors, windows, and handrails) on both levels 1 and 2.

Type of Project

Fit-Out and Remodelling

Summary of Services:

Furniture and Carpet Removal:
Cleared old items to make way for a fresh start

Floor Preparation:
Priming and levelling of subfloors

Partition Installation:
Added stud walls to define the new layout

Decorating:
Fresh paint on walls and ceilings

Sink Installation:
Lab-grade sink supplied and fitted

Conductive Flooring Installation:
Specialised flooring with added safety features

Deep Cleaning:
Complete clean-up of labs and pathways

Project and Safety Management:
Oversaw compliance and safety throughout the project