Case studies

Commercial

January 27, 2025

Project Value

Delivered within a competitive budget

Project Duration

4 Weeks

Key Elements

1. Transformation of a 650-square-foot open-plan cabin into three offices, a kitchen, and an entrance lobby.

2. Installation of acoustic-rated partitions to ensure a quiet and productive working environment.

3. Integration of modern mechanical and electrical systems, including new A/C units and energy-efficient lighting.

4. High-quality interior finishes, including new soft flooring, decoration, and bespoke furniture.

Seamless delivery of the project within a tight four-week timeframe on a live site, ensuring no disruption to GWR’s operations.

Type of Project

Commercial Office Refurbishment

Overview

This commercial fit out involved refurbishing a 650-square-foot infrastructure cabin at GWR’s Bristol Depot. The aim was to transform an open-plan space into a functional area comprising three offices, a kitchen, and an entrance lobby.

Scope Of Work

  • Installation of new acoustic-rated partitions.
  • Construction of new MF ceilings and wall linings.
  • Installation of new doors and ironmongery.
  • Design and installation of a new kitchen.
  • Comprehensive electrical and lighting installation.
  • Addition of new air conditioning units.
  • Installation of new soft flooring.
  • Interior decoration throughout.
  • Supply and installation of new furniture.

Key Phases

  1. Preparation: Site set-up and initial clearing of the open-plan cabin.
  2. Structural Works: Installation of partitions, ceilings, and skirtings.
  3. Mechanical and Electrical Installation: Integration of A/ c units and lighting systems.
  4. Finishing Works: Flooring, decoration, and kitchen fitting.
  5. Furniture Installation: Final placement of bespoke furniture.